RACI matrix: definition, example, templates and variants

What the four R, A, C and I roles mean, a ready-to-use example chart, the RASCI and RACI-VS variants, the classic mistakes and free Word and Excel templates. The simplest tool there is for making responsibilities clear in your projects.

What is a RACI matrix?

A RACI matrix is a project management and team management tool that spells out who plays which role on every task, decision or deliverable. RACI stands for Responsible, Accountable, Consulted and Informed.

It takes the form of a simple grid, with tasks in rows and people or roles in columns. Each cell shows who does the work, who signs it off, who gives input and who just needs to hear about the outcome. One glance is enough for everyone to see what is expected of them.

Why use a RACI matrix?

Unclear ownership is one of the most common reasons projects and cross-functional processes fail. When nobody knows exactly what belongs to them, tasks fall through the cracks, decisions stall and turf wars slow everything down.

A RACI matrix is especially useful in four situations:

  • Cross-functional projects that involve several teams or departments
  • Recurring processes (quality, HR, purchasing) where roles need to stay stable
  • Organisational change, when responsibilities are shifting
  • Onboarding new team members who need to understand quickly who does what

The four roles in a RACI matrix

R
Responsible

The person who does the work

The person (or team) who carries out the task and reports to the Accountable. A task can have more than one Responsible, but the fewer there are, the clearer the ownership.

⚠ Avoid stacking too many Rs on one task
A
Accountable

The person who answers for the result

The person who has the final say and is held to account for the outcome. They approve the Responsible's work. There can only be ONE Accountable per task: this is the most important rule in RACI.

⚠ One A per task, no exceptions
C
Consulted

The people asked for their expertise

People whose opinion or know-how is needed before the decision is taken or the work is done. This is two-way communication: the Consulted give input that can shape the task, but they do not carry it out.

Keep Cs to a minimum: every extra one slows things down
I
Informed

The people kept up to date

People who need to know about progress or the result, without taking part in the decision or the work. This is one-way communication, and the Informed group can be broad: senior management, customers, partners.

No influence on the task

RACI matrix example: a product launch

Here is a RACI chart for launching a new product, with five tasks and four typical stakeholders.

Task / activity Project manager Leadership Marketing IT
Set the launch objectives R A C I
Design the communication strategy C A R I
Build the technical platform C I I R/A
Approve the final budget R A I I
Run the launch and follow-up R/A I R C

R = Responsible  ·  A = Accountable  ·  C = Consulted  ·  I = Informed

How to build a RACI matrix in 5 steps

1

List every task and decision

Write down the key tasks, deliverables and decisions of the project or process. Not too granular (responsibilities get lost in the detail), not too high-level (you lose the precision you need). Aim for 10 to 30 rows on a typical project.

2

Identify everyone involved

Put roles (not necessarily named people) in the columns: project manager, IT, HR, quality team, leadership, customer. Include external parties where relevant. Keep the number of columns under control: beyond 8 to 10 stakeholders, the chart becomes hard to read.

3

Assign R, A, C and I

Fill in the right role at each task and person intersection. The golden rule: one A per row. Start with the Accountable, which is the most strategic choice, then the Responsible, then the Cs and Is.

4

Agree it with the stakeholders

A RACI matrix is only worth something if everyone accepts it. Hold a review meeting with all the people concerned: this is usually where grey areas and overlapping responsibilities come to light and get resolved.

5

Keep it up to date

The matrix evolves with the project. Review it whenever the organisation, the team or the scope changes. An outdated RACI is worse than none at all, because it gives a false sense of clarity about responsibilities that have moved.

RACI matrix variants

The classic RACI does not fit every situation. These are the variants teams use most often.

Standard

RACI

The basic version. It suits most projects and processes: simple, readable and quick to put together.

Extended

RASCI

Adds an S for Supportive (or Support): someone who helps the Responsible without owning the task. Useful on projects with a lot of cross-functional contributions.

Decision-focused

RACI-VS

Adds V for Verifier (who checks compliance) and S for Signatory (who formally signs off). Used in quality, regulatory and legal contexts.

Which variant should you choose?

  • RACI: a standard project, a team of fewer than 20 people, no regulatory constraints
  • RASCI: many cross-functional contributors, a matrix organisation
  • RACI-VS: ISO quality context, regulated process, approvals that must be traceable

For a detailed comparison, see our guide RACI, RASCI, RACI-VS: which variant is right for you?

5 classic RACI matrix mistakes

✕

More than one Accountable on a task

The most common breach and the most costly. As soon as a task has two As, nobody really owns it. The rule is absolute: one Accountable per row.

✕

Too many Consulted: paralysis by consultation

The more Cs on a task, the longer it takes. Every Consulted is a potential bottleneck. Limit Cs to the expertise you genuinely need: not everyone has to be consulted on everything.

✕

A matrix built without the team

A RACI handed down from above without discussion will be challenged or ignored. The value comes from building it together: the review is where disagreements about responsibilities surface and get settled.

✕

Mixing up Accountable and Responsible

The Responsible does the work. The Accountable answers for the result. A manager can be the A without doing the work; a team member can be the R without having the authority to decide. This distinction is the heart of the method: blur it and the matrix loses its value.

✕

Never updating the matrix

A RACI is a living document. A reorganisation, a change of scope or a new team makes it obsolete. A matrix nobody maintains creates false clarity, which is worse than having no matrix.

Built-in RACI in Perfony

The limit of a RACI chart in Excel or PowerPoint is that it is static. It describes who should be responsible at the time it was drawn up, but it does not follow what actually happens. Who really picked up the task? Who was kept informed? The spreadsheet has no idea.

Perfony builds the RACI logic into every action and every folder: each action has a single owner, contributors, observers and an approver, right inside your day-to-day follow-up, with no separate spreadsheet. It is the same logic you will find in our action plan software.

From a static RACI to a working RACI

In Perfony, RACI is not a governance document filed away somewhere: it is how every action is structured. Responsibilities are defined, tracked and recorded in real time.

✅

A Responsible on every action

Every Perfony action has a single owner (R). No ambiguity: the owner is notified, sees the action on their dashboard and gets an automatic reminder before the due date.

👁️

Contributors and observers

The C and I roles are handled natively: contributors can comment and update, observers are notified when the status changes but cannot edit.

📊

A consolidated RACI view per folder

The folder view lists every action with its owner: a living RACI matrix, updated in real time and available to the whole team.

🎙️

RACI built from your meetings

Perfony's AI meeting minutes pick out the actions agreed in the meeting and assign them to the person named. Your RACI builds up decision by decision, with no manual input.

Frequently asked questions

Can a task have more than one Responsible?
Technically yes, but it is not recommended. The more Responsibles there are, the less clear individual ownership becomes. If several people carry out the same task, split it into sub-tasks with one Responsible each, or name a lead Responsible who coordinates the others.
What is the difference between Accountable and Responsible?
The Responsible does the work. The Accountable answers for the final result, even if they do not do the work themselves. A director can be Accountable for a task without being the Responsible. The distinction matters because it separates doing the work from owning the outcome.
Which formats can you use to create a RACI matrix?
Excel and Word are the most common formats for a static matrix, and you can download free templates from our RACI templates page. For day-to-day, collaborative use, tools such as Perfony build the RACI logic into action tracking, with no separate file to maintain.
What is the difference between RACI and RASCI?
RASCI adds an S role, for Supportive or Support, covering people who help the Responsible without owning the task. It is useful in matrix organisations where shared resources contribute to several projects. For most projects, the classic RACI is enough.
How does Perfony handle the RACI matrix?
Perfony builds the RACI logic into every action: you can set a single owner (R), contributors (C or S), observers (I) and an approver (A). The folder view shows all actions with their owners, a living RACI matrix with no separate spreadsheet. You can try it free for 15 days.

A RACI that works, not just a spreadsheet

Free 15-day trial, no credit card required. Clear, tracked responsibilities in Perfony from today.